Renovation Bienengasse
The staircase has been renovated with the RenoProfil 8,5 mm Stabil profile and the Standard 8,5 mm profile in brass Eloxal.
As floor covering, the Tilolino 8 mm floor covering has been used.
The renovation of the existing stairs was not possible because the whole building is classified as a historical monument.
Within one week three floors, with 66 steps in all, have been renovated.
Tenants and other construction workers could use the stairs during the whole period of renovation.
![]() |
![]() |
| Before start of construction | Mount backup hand rail |
![]() |
![]() |
| Possibly remove front nosing |
(not necessary when working with Renoprofil Stabil profiles) |
![]() |
![]() |
| Remove old coverings | Remove front PVC edges |
![]() |
![]() |
| Screw on Renoprofil profiles | |
![]() |
![]() |
| Fix treads according to assembly instructions | Fix risers according to assembly instructions |
![]() |
![]() |
| Fix wooden panels in the front | Clean the stairs |
![]() |
![]() |
|
Seal all joints with joint seal |
Finished |
![]() |
We hope we have been able to show you how to renovate a staircase in an understandable way.
In case you have any further questions, please do not hesitate to contact us.
You can reach us at all times
Your Renoprofil Team